BHI
FaxSheet
THE BIG
DIG: A BIG LESSON
May
1993
President Clinton has expressed an intention to spend $80 billion on
new government projects in the belief that such projects represent investments
in U.S. productivity and competitiveness. Included in his plans are
mega projects like data networks, superhighways and high-speed rail
lines, as well as less spectacular projects for repairing roads and
bridges and renovating airports.
Is
this massive government spending the way to rebuild the economy? A dollar
taken by the government for an "investment" project or any
project is a dollar denied private investors. The question is whether
the government project offers a rate of return (measured in benefits
to society) at least equal to that offered by the private project it
displaces.
Some
government projects are no doubt justifiable. There is evidence for
example, that projects that keep the current system moving smoothly
- fixing pot-hole ridden and dangerous roads for instance- represent
a sound investment. The larger and more spectacular mega-projects that
are so appealing to politicians are, however, another matter.
Private
investors are accountable to creditors, partners or stockholders for
producing a competitive return on investment. Not so for government,
which is inclined to pork-barrel spending and special-interest pandering.
A project that, if privately funded, offers a competitive rate of return
can, in the hands of government, easily turn into an expensive, open-ended
boondoggle.
For
a lesson on the economics of government "investment," consider
the great Massachusetts investment project of the 90s- the Big Dig.
This government project aims to turn the maze of elevated highways now
running through downtown Boston into a smooth-running and environmentally-safe
underground highway system. It provides for a third Boston Harbor tunnel
that will relieve traffic congestion heading to Logan International
Airport and other locations to the north of Boston and the construction
of a series of bridges crossing the Charles River that will alleviate
congestion in traffic west of Boston.
A
History Lesson on "Infrastructure" Spending
The 1987 Federal Highway bill created the Big Dig, more formally known
as the Massachusetts Central Artery/ Third Harbor Tunnel (CA/T) project.
Shortly after it was approved officials estimated costs at $3.3 billion
with a time frame of 11 years until completion. Construction would begin
in 1988. The existing surface artery through downtown Boston would be
ripped up in 1989, and construction of a third Boston Harbor tunnel
would begin in 1990. Construction of the Charles River crossing would
be under way in 1993, the new harbor tunnel would open for travel in
1994, a new northbound depressed artery would open in 1995 with a southbound
portion following in 1996. Workers would begin dismantling the old elevated
highway in 1997 and the whole project would be completed in 1998.
Since
1983, however, cost estimates have risen by 132 percent in actual dollars
and by about 65 percent in "constant," inflation-adjusted
dollars. Moreover, the schedule is off by more than two years. If costs
continue to increase at the current rate, approximately 9 percent annually,
the cost of the project at completion in the year 2002 will exceed $12.4
billion.
The
cost of the CA/T project will be split approximately 85 percent-15 percent
between the federal government and the state. Cost estimates are determined
by jointly by the Federal Highway Administration and state officials.
The 85-percent federal share of the cost will be funded through the
national gasoline tax. Massachusetts expects to pay for its 15-percent
share through the state's gasoline tax and through a hefty toll of $2-$3
at the new tunnel. No more than 2 cents of the state's gasoline tax
- approximately $50 million annually - is earmarked for artery and tunnel
funding. Federal funding is guaranteed only through 1997.
Official estimates of the cost to Massachusetts have grown from $250
million in 1987 to the current estimate of approximately $870 million.
(If total project cost ultimately rises to $ 12.4 billion as considered
above, the cost to the state will rise to $1.86 billion.)
The
following table provides a history of official CA / T project cost estimates
from both federal and state officials and CA / T officials. The current
CA / T estimate stands at $5.8 billion.
Schedule
of Cost Estimates
|
Date
|
Estimate
|
Comment
|
|
1
/ 83
|
$2.5
B
|
Initial
estimate developed by federal and state officials.
|
|
1
/ 87
|
$2.5
B
|
Federal
approval of funds for CA/ T project.
|
|
2
/ 87
|
$3.3
B
|
Increase
in statewide construction costs.
|
|
3
/ 88
|
$4.3
B
|
Increase
due to changes in design, inflation and increased real estate
values.
|
|
9
/ 88
|
$4.4
B
|
Increase
due to design improvements, increased real estate values and statewide
inflation in construction costs.
|
|
7
/ 90
|
$5.0
B
|
Increase
due to inflation, higher environmental costs, additional materials
to protect against earthquakes and design changes.
|
|
6
/ 92
|
$5.8
B
|
Increase
due to inflation and unexpected problems
|
|
5
/ 93
|
$5.8
B
|
Current
estimate.
|
Current
Status
According to the Massachusetts Highway Department, there are currently
eight major construction contracts under way in the CA / T project,
valued at $800 million. Construction of the third-harbor tunnel has
been under way for 14 months with the first section of the tube tunnel
put into place on February 3. There are also gas and sewerage utility
relocations under way, both of which are preliminary projects for the
artery depression segment.
Plans for construction of the Charles River crossing lane have not been
finalized. The original construction plan, known as "Scheme Z,"
is a 16-lane, 11-story-high structure currently estimated to cost $1
billion. At the onset of this project, Scheme Z was estimated at $400
million. Any alternative design Scheme Z, under consideration, will
be more expensive and add to the project estimate.
Observation
There are numerous costs involved in the CA / T project besides the
ones we have noted above. Among these are disruption to downtown business
during construction, revenues lost as a result of decreased access to
downtown business establishments and confusion caused by rerouting of
traffic.
The
record of unanticipated costs and delays described above provides an
object lesson on government "investment" spending. The market
test of the economic viability of an investment project is that it yield
a rate of return higher than that yielded by other projects that compete
for the investor's dollar. The higher the cost and the longer the period
to completion of any investment project, the lower its rate of return.
One must ask, in the light of its history of cost overruns and delays,
whether the CA / T project offers a rate of return that is as high as
that offered by other private and public projects that are necessarily
being sacrificed as investment dollars are diverted from those projects
to the CA / T.
Indeed,
it might be appropriate to think of certain government mega-projects
as "disinvestments": exercises in putting investment dollars
into public projects that offer cost overruns and delays and away from
private projects that offer competitive rates of return. As for the
Big Dig, it will go on and on, taking U.S. and Massachusetts taxpayers
for a long and costly ride.
Information
for this paper was obtained from various articles in the Boston Globe,
1986-1993, and from material obtained from the Massachusetts Highway
Department.